Displaing rhombus in gantt

In your ejGantt control, the left corner of the rhombus representing a task made in one moment is placed at that moment, while the bottom corner (middle) should be placed there. Now it looks like task has been made later than it actually has. E.g. task started and finished at 6:00 PM looks like it has been made later than finish of a task started at 10:00 AM and finished at 10:00 PM.

Below I paste few screens, and jsPlayground:


Now: 




Expected:
expected
Regards,
Karol

3 Replies

SR Suriyaprasanth Ravikumar Syncfusion Team August 9, 2017 09:21 AM UTC

Hi Karol, 
 
Please find the response below. 
In Gantt currently milestone task are rendered with start date value with respective to left corner of rhombus. 
As per your request we have logged improvement task to render milestone task with respective to center of the rhombus with start date value. 
These changes will be done and included in our upcoming volume 4, 2017 main release which will be expected to out at end of October, 2017. 
 
Thanks, 
Suriyaprasanth R. 



KW Karol Wlodarek August 9, 2017 02:40 PM UTC

Thanks for the answer,

I am looking forward to the amendments with impatience.

Regards,

Karol



SR Suriyaprasanth Ravikumar Syncfusion Team August 10, 2017 12:02 PM UTC

Hi Karol, 
 
As per your request a support incident has been created under your account to track the status of this requirement. 
Please log on to our support website to check for further updates. 
 
Please let us know if you require further assistance on this.

Regards
 
Suriyaprasanth R. 