Workweek weekdays but allow only one saturday as workday
We have the default workweek as weekdays (monday to friday) but we need to allow only one saturday as workday and reflect it on gantt calculation!
Hi Bruna,
Greetings from Syncfusion Support,
We have reviewed the
query on our end. It is not possible to achieve your requirement of considering
only a specific Saturday as a working day in the Gantt chart validation. Our
validation does not support specific date-based working days. However, the workWeek
property can be used to consider all Saturdays as working days in the overall
timeline. We have attached a code snippet and sample for reference:
|
<GanttComponent id='Editing' dataSource={editingData} workWeek={workWeek} > ... </GanttComponent> |
You can find a working example on
StackBlitz.
For more information, you may refer to the following link:
https://ej2.syncfusion.com/react/documentation/api/gantt/#workweek
If you have any further questions or need additional assistance, please let me
know!
Regards,
Ajithkumar G
Hi,
The problem in this case is that gantt will consider every Saturday as workday and this is a problem, in my case, the default saturday is not considered, but as overtime workday, there is any way or workaround?
thanks
Hi Bruna,
We have already
explained that considering a specific Saturday as a working day in the Gantt
chart is not feasible, and workaround for this requirement also not
possible. We already logged feature request for the
requirement as uncertain. You can track the
status of the feature from the feedback link given below.
Feedback link - https://www.syncfusion.com/feedback/64871/provide-support-to-set-specific-weekend-as-a-working-day-in-a-timeline
We have already lined up some major features, we could not implement this support immediately. We will implement this and include it in any of our upcoming releases. Please cast your vote on this feature. Based on the customer demand we will prioritize the features in our upcoming road map. You can communicate with us or track the status of the feature using the feedback link.
If you have any further questions or need additional
assistance, please let me know!
Regards,
Ajithkumar G
You can set the default workweek to Monday–Friday and manually define one Saturday as a workday in your scheduling settings. If you're using MS Project or another Gantt tool, try adjusting the Work Calendar or Exception Days to allow only one Saturday. Hope this helps!
Surah,
For your query, we understand that you expect only one specific Saturday to be a working day. Other Gantt tools may support this feature, but in the Syncfusion Gantt Chart, this functionality has not been implemented yet.
A feature request has already been logged and it will be implemented in any of our releases. You can track the status of this feature request using the feedback link provided below.
Feedback link - https://www.syncfusion.com/feedback/64871/provide-support-to-set-specific-weekend-as-a-working-day-in-a-timeline
Please get back to us if you need any other assistance
Regards,
Sridharan
You can set the default workweek to Monday–Friday and manually define one Saturday as a workday in your scheduling settings. If you're using MS Project or another Gantt tool, try adjusting the Work Calendar or Exception Days to allow only one Saturday. Hope this helps! Locksmith York
For your query, we understand that you expect only one specific Saturday to be a working day. Other Gantt tools may support this feature, but in the Syncfusion Gantt Chart, this functionality has not been implemented yet.
- 6 Replies
- 5 Participants
-
BL bruna luiza mokwa
- Feb 18, 2025 05:18 PM UTC
- Sep 19, 2025 06:31 AM UTC