When we set up the Workweek, assuming Monday to Friday as working days, the entire Gantt chart is fixed with only Monday to Friday as workdays. However, if some projects require overtime on Saturdays (non-fixed), while others do not, this design may result in inaccuracies in calculating work hours for projects that do not require overtime. Is there any way to solve this problem?
Hi Lumax,
Greetings from Syncfusion.
After reviewing your query, currently do not have support to set different dayWorkingTime for each day in Gantt functionality.
We already logged feature request for the requirement. You can track the status of the feature from the feedback link given below.
Feedback link: Provide support to set dayWorkingTime for each day in JavaScript | Feedback Portal (syncfusion.com)
We will implement this feature and include it in any our upcoming releases. You can communicate with us or track the status of the feature using the feedback link.
Until we appreciate your patience.