Hi Meissa,
Greetings from Syncfusion
We have thoroughly reviewed your query and have identified
two possible scenarios that might be causing this issue.
The first scenario occurs when you map the duration of the
task. In this case, our system gives high priority to the duration, and the
taskbar is rendered based on the specified duration. This could be the reason
why the start and end dates are not aligning with your endpoint date.
The second scenario arises when the start date and end date
fall on weekends or holidays. To ensure accurate rendering, we internally
validate and adjust the taskbar with updated dates in such cases. However, if
you wish to include weekends in the date calculations, you can achieve that by
setting the "includeWeekend"
property to true. This will ensure that the weekends are considered as
working days in your Gantt chart.
|
Code
Snippet:
/*app.component.html*/
<ejs-gantt
[includeWeekend] = "true"
>
|
Sample Link : https://stackblitz.com/edit/angular-pzavnt?file=src%2Fapp.component.html
We hope that by following these guidelines, you will be able
to resolve the issue you have encountered. Should you require any additional
assistance or have further questions, please do not hesitate to reach out to
us.
Regards,
Udhayakumar