- when editing a task with the dialog box, is it possible to ignore weekends in the automatic calculation of the end date
here is the scenario:
- we choose a start date for example 8/21/2020, it falls on a Friday
- then, we modify the duration of the task, for example 4 days
normally the end date should be 08/26/2020 because we do not count the weekend
but in the current case he puts 8/24/2020 which implies that he has counted it with weekends