how does critial path work?

Thread ID:

Created:

Updated:

Platform:

Replies:

132470 Sep 4,2017 05:48 AM Sep 5,2017 12:47 PM ASP.NET MVC 1
loading
Tags: Gantt
Manolo
Asked On September 4, 2017 05:48 AM

Hi,

I can't understand the critical path.

I this gantt... why the first tasks are not critical path? Only task 11 is critical.... why?


Suriyaprasanth Ravikumar [Syncfusion]
Replied On September 5, 2017 12:47 PM

Hi Manolo, 
The critical path in a project is indicated by a single task or a series of tasks in a project, critical path describes the calculated start date or end date of a project. If a task in a critical path is delayed, then the entire project will be delayed. 
We have implemented this support based on the MS Project. 
We have analyzed the provided screenshot, the task 11 is laid at the end date of the project, if we change that task the project end date get affected, hence it is marked as critical task. 
While on moving the first task it does not affect the project end date hence it is not a critical task. 
Please let us know if you need any other assistance.  
 
Thanks, 
Suriyaprasanth R.

CONFIRMATION

This post will be permanently deleted. Are you sure you want to continue?

Sorry, An error occured while processing your request. Please try again later.

You are using an outdated version of Internet Explorer that may not display all features of this and other websites. Upgrade to Internet Explorer 8 or newer for a better experience.

;