We use cookies to give you the best experience on our website. If you continue to browse, then you agree to our privacy policy and cookie policy. Image for the cookie policy date

Baseline and Null Dates

Hi,
I am having a problem when in a Gantt there is a Baseline that has a null limit in the dates.
The Range of data in that case starts from 1969 to today so the data in the Gantt is showed in bad format.
Is this a bug (maybe not showing the Baselines if the dates are null or is it a behavior that we need to work with?
If so, there is a workaround?

I Uploaded a video with the problem.

    Thanks in advance

    Andrea Perazzolo

Attachment: 20151028_at_095959_4eac1d17.zip

1 Reply

DK Dinesh Kumar Nagarathinam Syncfusion Team October 29, 2015 09:16 AM UTC

Hi Andrea,
We were able to reproduce the issue in baseline with null values and we have confirmed this as bug and logged a report on this. Also we have created a support incident under your account to track the status of this issue.
Please log on to our support website to check for further updates.
https://www.syncfusion.com/account/login?ReturnUrl=%2fsupport%2fdirecttrac%2fincidents
Please let us know if you require further assistance on this.

Regards,
Dinesh kumar.N