Parent Tasks In Resource View

Hi,

In resource view, parent tasks are not visible. Is there any way to show them ?


1 Reply 1 reply marked as answer

AK Alagumeena Kalaiselvan Syncfusion Team January 7, 2022 01:22 PM UTC

Hi Halit, 
 
The current behavior of resource view is used to visualize the tasks assigned to each resource in a hierarchical manner. In this view, we will render each resource as a parent and the tasks assigned to it will be rendered as its child records. Hence only the child records (actual tasks) has task bar and parent records (resource details) does not have one. Please refer to our online documentation for more information. 
 
 
 
Regards, 
Alagumeena K 