Gantt chart holidays

Hi 

I add holidays/resting days to GanntChart with this code:


code.png

Works great with version 19.4.0.38.

latszik.png


But 19.4.0.40. and 19.4.0.41 version there is nothing visible (same date, same code)


nem_latszik.png


What could be the problem ?

Thank you in advance for your help !

Greetings from Hungary !



3 Replies

AK Alagumeena Kalaiselvan Syncfusion Team January 5, 2022 12:18 PM UTC

Hi Szoke, 

Greetings from Syncfusion support. 

We have checked your reported query in 19.4.0.40 and 19.4.0.41 versions but unfortunately we could not replicate the issue at our end. We have shared the sample for reference. 

Kindly try to share below details to proceed further 
  • Share the code snippet of your sample
  • Reproduce the issue in shared sample
  • Share the issue replicating sample if possible

Regards 
Alagumeena.K 



SZ Szoke replied to Alagumeena Kalaiselvan January 5, 2022 07:41 PM UTC

Hi!

With HTML 


<GanttHolidays>
        <GanttHoliday From="@Holiday1" To="@Holiday2" Label="Public holidays"></GanttHoliday>
        <GanttHoliday From="@Holiday3" To="@Holiday4" Label="Public holiday"></GanttHoliday>
</GanttHolidays>

works fine for mee to.


But , if I define from code:

SfGant.Holiday.Add ( new GantHoliday() {...



the result is not visible in GanttChart (from 19.4.0.40 version).




AK Alagumeena Kalaiselvan Syncfusion Team January 6, 2022 01:43 PM UTC

Hi Szoke, 

Thanks for your update. 

We have checked your reported query and we could replicate the issue at our end. So, we have confirmed this scenario as defect and logged defect report. You can track the issue status using below link. 

We will fix the issue and included in weekly patch release on  26th January, 2022. 

Regards 
Alagumeena.K 