ScheduleRangePadding not update

Hi,

if i change the start date the schedule range not update, but if i change also the ned date it changes, why?


Best regards

Gian Piero Truccolo


Attachment: ScheduleGanttRangeNotUpdate_aa30b08.zip

2 Replies

SS Sridevi Sivakumar Syncfusion Team June 25, 2021 03:11 PM UTC

Hi Gian Piero Truccolo,

Greetings from Syncfusion.

We checked the reported issue Schedule finish date not get updated while changing task's start date beyond the schedule's finish date and we have logged a bug report for this issue. You can keep track of the bug from the feedback portal below.

Link: https://www.syncfusion.com/feedback/26488  

The provided feedback link is private, and you need to login to view this feedback.

We will fix this issue and provide the patch on July 1,2021.

If you have any more specification/precise replication procedure or a scenario to be tested, you can add it as a comment in the portal.

Regards, 
Sridevi S.   



SS Sridevi Sivakumar Syncfusion Team July 6, 2021 10:42 AM UTC

Hi Gian Piero Truccolo,

We have fixed the “
Schedule finish date not get updated while changing task's start date beyond the schedule's finish date” issue and the fix is included in our weekly NuGet of July 6, 2021.

NuGet Version: 19.2.0.46

We thank you for your support and appreciate your patience in waiting for this release. Please get in touch with us if you would require any further assistance.

Regards,
Sridevi S.
 
 


Loader.