Hi,

We have a requirement where a task can be worked upon by the resource based on their availability. For example, they may work only on Mondays and Wednesdays. In such cases, I need to display a task in segments on the same row. I referred the documentation, but didn't found a way to do so.

It would be helpful if you can please guide us on how to achieve it.

Below image demonstrates our requirement where task 2 is split into three segments.


Thanks,
S.R.

2 Replies

KR Karthikeyan Raja Syncfusion Team February 19, 2020 04:14 PM UTC

Hi Sanjay, 

We have already logged a feature report for this, you can track its status from below feedback report link. 
As we have already lined up with some major features, we could not start this feature immediately. We will implement this support and include in any our upcoming releases. 
Please cast your vote to make it count. We will prioritize the features for every release based on demands. 
 
Please get back to us if you require further assistance on this. 
  
Regards, 
Karthikeyan Raja 



GM Gopinath Muniraj Syncfusion Team December 18, 2020 11:33 AM UTC

Hi Sanjay, 
 
We are glad to announce that our Essential Studio 2020 Volume 4 release v18.4.0.30 is rolled out and is available for download under the following link. 
 
In that release, we have included the feature of “split tasks” which is mentioned in the feedback link 8585. Please refer the below Sample browser to get more information. 
 
 
We thank you for your support and appreciate your patience in waiting for this release. Please get in touch with us if you would require any further assistance. 
 
Regards,            
Gopinath M 