Hi,
We have a requirement where a task can be worked upon by the resource based on their availability. For example, they may work only on Mondays and Wednesdays. In such cases, I need to display a task in segments on the same row. I referred the documentation, but didn't found a way to do so.
It would be helpful if you can please guide us on how to achieve it.
Below image demonstrates our requirement where task 2 is split into three segments.


Thanks,