Predecessor tasks with lag

Hi!
|In my project we need to create task scheduling using Predecessor Lag (Examples: 153FS+5d, 44SS-2d). Is it posible to be represented in Predecessors column and in Gantt chart?

Thanks in advance.

Dalton.

1 Reply

RA Riyaj Ahamed I Syncfusion Team July 3, 2013 11:09 AM UTC

Hi Dalton,

Thanks for contacting Syncfusion support.

We have analyzed your query. As of now we do not provide support to schedule the task through Predessor column. However you can schedule the task through Start and End columns.

Please let us know if you have further queries.

Regards,
Riyaj Ahamed I