Setting Custom Calendars for tasks

Hi!
I need to set custom calendars for each task in my project including set custom nonworking days and times(example: Saturday is a half-turn working day, national, state and city holydays). Is it possible? if it is, how do I do it? Otherwise, is there any kind of workaround?

1 Reply

RA Riyaj Ahamed I Syncfusion Team July 3, 2013 10:55 AM UTC

Hi ,

We have analyzed your query. You can set the custom calender by using custom scheduling. To know more about custom scheduling please refer the following link,

UG Link: http://help.syncfusion.com/ug/wpf/gantt/default.htm#!documents/customschedule.htm

Our GanttControl enables you to mark the custom regions in GanttChart area using Striplines. To know how to add strip lines in GanttChart region please refer the following UG link,

UG Link: http://help.syncfusion.com/ug/wpf/gantt/default.htm#!documents/striplines.htm 

Please let us know if you need further assistance.