  1. Run the sample.
  2. Add a task to the gantt, via add task dialog, change scheduling type to fixed work, set work to 8, assign one resource.
  3. Click save in dialog
  4. Right click on created task, add a child task
  5. Open edit task dialog for added child.
  6. Ensure scheduling type is fixed work, 8 hours, and add 2 resources.
  7. Click Save in dialog.
  8. Right click on the child task, and outdent it.
  9. Observe that both child and parent now show work of 8 hours:
  10. Open edit dialog for the parent task, update the name of the task.
  11. Click Save
  12. Observe that work now recalculates correctly as it should have on outdent: